• $
  • €
  • ₽
  • ₺
  • £

Gary Jones: First ACE oil to be delivered in early 2024

Gary Jones: First ACE oil to be delivered in early 2024
04.04.2023 13:30
bp as operator of the Azeri-Chirag-Deepwater Gunashli (ACG) field development project today welcomed H.E. Ilham Aliyev, President of the Republic of Azerbaijan, to the Bayil fabrication yard where the topsides unit of the Azeri Central East (ACE) platform has been built, reported from the company.

Gary Jones, bp’s regional president for Azerbaijan, Georgia, and Türkiye, said: "It was an honour for us to host President Ilham Aliyev at the ACE topsides fabrication site today and tell him about the great progress the project has been making.

"The topsides unit is the final major step the project is currently taking towards full completion. We expect topsides onshore construction and commissioning works to be completed in the second quarter of this year. Once fully completed and operationally tested the unit will be loaded out onto the transportation barge STB-1, transported to its permanent location and installed onto the jacket which is already at the field. We will then need a few months to complete offshore commissioning works and drill the first platform well to deliver the first ACE oil early 2024.

"I would like to thank President Aliyev and his government for the invaluable support they have given us throughout the project. My thanks are also to SOCAR and our partners for their support and all people representing bp, Azfen, other contractors and subcontractors for their contribution to the safe and efficient delivery of the project.”

The President toured the ready facility and officially launched the ACE topsides unit which will sail away for offshore installation in the second quarter of 2023.

The ACE topsides facilities have a design weight of 19,600 tonnes containing oil and gas processing facilities, an integrated drilling rig, a gas compressor and living quarters.

The topsides unit has been constructed by Azfen in the Bayil fabrication yard using local infrastructure and resources. Currently, construction and commissioning works are in the final stages with 95% of overall onshore commissioning works already completed.

At peak, the topsides construction activities involved up to 4,400 workers and over 90% of them were Azerbaijani nationals.

The safety record at the site has been outstanding - the topsides team recently celebrated 20 million hours worked without injury.

The ACE project is the next stage of development of the giant Azeri-Chirag-Gunashli (ACG) field in the Azerbaijan sector of the Caspian Sea. It is a $6 billion development project which includes a new offshore platform and facilities designed to process up to 100,000 barrels of oil per day. The project is expected to produce up to 300 million barrels over its lifetime.

The project was sanctioned in April 2019. The sanction of ACE was the first major investment decision by the ACG partnership following the extension of the ACG Production Sharing Agreement (PSA) to 2049 was agreed in 2017. Around $42 billion has been invested in the development of the ACG area since the original PSA signed in 1994.

The ACE project is centred on a new 48-slot production, drilling and quarters platform located mid-way between the existing Central Azeri and East Azeri platforms in a water depth of approximately 140 metres. The project also includes new infield pipelines to transfer oil and gas from the ACE platform to the existing ACG Phase 2 oil and gas export pipelines for transportation to the onshore Sangachal terminal.

In addition, there is a water injection pipeline installed between the East Azeri and ACE platforms to supply injection water from the Central Azeri compression and water injection platform to the ACE facilities.

The ACE platform is designed to use technology innovations and automated operation systems that will be controlled remotely from an onshore control room at the Sangachal terminal. It will be the first remotely operated offshore platform in the Caspian. Currently, the remote control scope at the Sangachal terminal is 100% complete with the control room already operational allowing testing to take place.

Construction activities for the project commenced in late 2019 and have taken place in-country utilizing local resources. At peak, over 8,500 people were involved in overall construction activities in Azerbaijan.

Currently, some 85% of the project work scope has been completed with over 25 million hours worked injury free.

www.anews.az
Facebook
Go
Similar news
Similar news
Azerbaijan to include deep-lying ACG gas output in energy balance from 2027
Business 16:01
Azerbaijan to include deep-lying ACG gas output in energy balance from 2027
Tanker Khankendi makes historic first entry into Australian waters under Azerbaijani flag
Business 15:37
Tanker Khankendi makes historic first entry into Australian waters under Azerbaijani flag
SOCAR expects to disclose ACG recoverable gas volumes soon
Business 15:00
SOCAR expects to disclose ACG recoverable gas volumes soon
SOCAR, BP see ACG’s ultimate oil recovery factor above 40%
Business 14:30
SOCAR, BP see ACG’s ultimate oil recovery factor above 40%
BP says ACG annual oil output decline slows to 3%
Business 13:58
BP says ACG annual oil output decline slows to 3%
Azerbaijan central bank sets official exchange rates for November 13
Business 13:00
Azerbaijan central bank sets official exchange rates for November 13
Gold prices rise 0.7% to $3,912.4 per ounce on COMEX
Business 12:30
Gold prices rise 0.7% to $3,912.4 per ounce on COMEX
Azerbaijan gas pipeline to Europe operating at full capacity, Aliyev says
Business 12:29
Azerbaijan gas pipeline to Europe operating at full capacity, Aliyev says
Oil prices edge lower on easing geopolitical tension hopes and rising US stocks
Business 12:00
Oil prices edge lower on easing geopolitical tension hopes and rising US stocks
Anews TV

Our official Youtube channel

Subscribe